Route 219 Expressway Phase2 (Morrow Road to Route 108)

Description: Route 219, from Morrow Rd to Route 108 - Widen to 4-lane expressway.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City
Zip Code 95356
 
Senate District
14
Assembly District 25
Congressional District 19
 
Caltrans District
10
 
 
County/State Route Stanislaus 219
Postmile Begin/End 2.9 4.9
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  1302      
Lane Miles Added (Mixed)  21.73      
Peak Period Time Savings (minutes)  51851      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Sinarath Pheng (209) 948-7829   sinarath.pheng@dot.ca.gov
Design (PS&E) Phase
Caltrans Sinarath Pheng (209) 948-7829   sinarath.pheng@dot.ca.gov
Right of Way Phase
Caltrans Sinarath Pheng (209) 948-7829   sinarath.pheng@dot.ca.gov
Construction Phase
Caltrans Sinarath Pheng (209) 948-7829   sinarath.pheng@dot.ca.gov
 
Corridor System Management Plan
Caltrans Lynn O'Connor (209) 948-3975   lynn.oconnor@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $1,528 $1,528
CMIA
$18,813 $-5,572 $13,241
Non-bond Funding
State/Federal*
$29,447 $-6,034 $23,413
Local**
$2,240 $2,240 $4,480
Non Budgeted ETC
$0 $0 $0
 
Total**** $50,500 $-7,838 $42,662

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $0 $0 $0
Design(PS&E)
$2,000 $1,100 $3,100 $3,154
Right of Way
$19,000 $-1,350 $17,650 $23,999
Construction
$29,500 $-7,588 $21,912 $20,615
 
Total* $50,500 $-7,838 $42,662 $47,767

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/1998 

05/01/2004 
 

 
10/01/1998 

05/01/2004 
100  10/01/1998 

05/13/2004 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2004 

04/01/2009 
 

 
10/01/2004 

06/30/2010 
100  04/02/2007 

06/30/2010 
-30 

Begin Right of Way Phase

End Right of Way Phase
01/01/2005 

06/01/2009 
 

 
01/01/2005 

11/01/2011 
75  01/01/2005 

11/07/2011 


Begin Construction Phase

End Construction Phase
12/01/2009 

12/01/2011 
 

 
05/30/2012 

05/30/2014 
100  08/30/2012 

10/30/2015 
-3 

-17 
Begin Closeout Phase

End Closeout Phase
02/01/2012 

03/01/2012 
 

 
07/31/2014 

07/31/2015 
75  11/24/2015 

05/07/2019 
-16 

-46 
Corridor System Management Plan
Adoption Date 10/01/2008    10/01/2008  04/06/2011  -31 
Implementation Date 02/01/2009    02/01/2009  05/06/2011  -27 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 1302
Lane Miles Added (Mixed) 21.73
Peak Period Time Savings (minutes) 51851

Bond Funding Cost
Adopted:
$18,813,000
Current Approved:
$13,241,000
Actual Expenditures:
$12,086,000

 

Status as of December 31, 2023.